BR 01 PS 0005Patna, Bihar31 March 2025

Patna Smart City Limited (PSCL)

Patna Smart City Limited is the Special Purpose Vehicle (SPV) for Patna under the Smart Cities Mission, headed by a CEO to implement city projects. Patna was one of four Bihar cities selected and was selected in June 2017, in the round that added 30 cities. The Mission period was extended up to 31 March 2025 to complete remaining projects; PSCL still listed open tenders in September 2026. A CAG audit noted that of 44 initially approved Patna projects, 29 had not started by October 2022.

OperatingV2
What this record means

This page is a factual profile built from official sources: enterprise filings, the DPE Public Enterprises Survey, PIB releases, government orders and CAG reports. Figures carry their year; where no official figure was found, the field is left out rather than estimated.

How we verify →

Patna Smart City Limited is the Special Purpose Vehicle (SPV) for Patna under the Smart Cities Mission, headed by a CEO to implement city projects. Patna was one of four Bihar cities selected and was selected in June 2017, in the round that added 30 cities. The Mission period was extended up to 31 March 2025 to complete remaining projects; PSCL still listed open tenders in September 2026. A CAG audit noted that of 44 initially approved Patna projects, 29 had not started by October 2022.

What happened

SPV and ownership: PSCL describes itself as a Companies Act, 2013 SPV that plans and implements Patna Smart City projects. Its official site names the Government of Bihar's Urban Development & Housing Department and Patna Municipal Corporation as promoters with 50:50 equity.

Selection and audit: The CAG report identifies Patna among four Bihar smart cities and says Patna was nominated for the Mission in June 2017. It reports that 29 of 44 approved Patna projects could not be started by October 2022, citing projects already being executed by other agencies, unavailable land, rooftop farming being unnecessary, and likely crowding in already crowded areas.

Mission and current activity: PIB says the Mission period was extended up to 31 March 2025 to complete remaining projects. PSCL's official tender page listed open tenders with September and October 2026 deadlines.

What we could not confirm

The opened official sources confirm the 50:50 promoter split and show PSCL tenders after the Mission period ended. They do not provide the company's paid-up share capital amount, standalone current financial statements, or employee count.